Finished pouring the slab and building the interior walls in the community building. 250 more sacks of cement. Begin building walls on the interior of the main building, nearing the end of the interior demolition. Began the layout of the second floor plumbing and located all plumbing drops on the first floor. Began trenching for the plumbing on the main floor.