May 4-May 8, 2009

The week begins with placing the window lintels and building the walls in preparation for the trusses. After the trusses were finish welded and ground smooth, they were painted. 1000 more block were ordered bringing the total to 4500 block to date. We begin backfilling the footings along the security wall. The community building walls were completed and readied for trusses. The rains began in earnest.