July 13-July 17,2009

Work was begun on the Community Building patio. The stone terrace upper wall was completed and the lower terrace wall begun. Electrical and rough plumbing were begun in Apartments #2 & 3, and Apartment #4 was completed. The exterior of Apartment #4 was finish stuccoed. Work continued in the Cabinet shop.